1 |
gpfplc |
Urea |
MT |
924000 |
2847 |
72786 |
546361 |
900000 |
353639 |
76000 |
0 |
|
2 |
sfcl |
Urea |
MT |
580000 |
1140 |
33050 |
159557 |
500000 |
340443 |
43000 |
0 |
Less production due to process inherent problem in urea plant. |
3 |
jfcl |
Urea |
MT |
561000 |
0 |
0 |
0 |
315000 |
315000 |
27000 |
0 |
Plant shutdown on 15/01/2024 due to NG (Natural Gas) supply pressure abnormally low from TGTDCL. |
4 |
cufl |
Urea |
MT |
561000 |
1195 |
9315 |
51878 |
350000 |
298122 |
31000 |
0 |
|
5 |
afccl |
Urea |
MT |
528000 |
0 |
2092 |
2092 |
240000 |
237908 |
21000 |
0 |
Urea production stopped at 15:00 hrs on 25.01.2025 due to low ammonia stock. Syn Gas compressor maintenance works are going on in ammonia plant. |
Total | Urea | MT | 3154000 | 5182 | 117243 | 759888 | 2305000 | 1545112 | 198000 | | |
6 |
tspcl |
TSP |
MT |
100000 |
310 |
9055 |
29745 |
110000 |
80255 |
9000 |
0 |
|
7 |
dapfcl |
DAP |
MT |
528000 |
0 |
0 |
29957 |
150000 |
120043 |
12700 |
0 |
DAP-1, 0,. Production stopped due to shortage of phosphoric acid.
DAP-2: 0, Production stopped due to shortage of phosphoric acid.
|
8 |
kpml |
Paper |
MT |
30000 |
0 |
203.13 |
685.91 |
5000 |
4314.09 |
420 |
0 |
Production stopped due to shortage of raw materials. |
9 |
cccl |
Cement |
MT |
190000 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Production stopped on 12/05/2021 due to shortage of limestone & fresh clinker. |
10 |
ugsf |
Sheet Glass |
L.Sq.M |
18 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Production stopped on 21/08/2023 due to gas disconnection from Furnace and shutdown of Furnace no.-2. |
11 |
bisf |
sanitary |
MT |
3400 |
1.42 |
39.47 |
411.21 |
1260 |
848.79 |
106 |
0 |
|
insulator |
MT |
1700 |
0 |
0 |
0 |
900 |
900 |
76 |
0 |
Production stopped on 19/04/2023 due to lack of sales order. |
refractories |
MT |
1700 |
0.2 |
4.37 |
91.84 |
210 |
118.16 |
18 |
0 |
|